HBA-ALS H.B. 1343 76(R)    HBA-ALS, ALS, ALS H.B. 1343 76(R)     BILL
ANALYSIS 


Office of House Bill AnalysisH.B. 1343
By: Dukes
State Affairs
3/31/1999
Introduced



BACKGROUND AND PURPOSE 

A study commissioned by in the 73rd Legislature found that prime
contractors were not meeting their negotiated Texas historically
underutilized business (HUB) goals.  In addition, a state auditor's report
in 1998 found that prime contractors did not suffer a loss or pay a penalty
for low HUB participation, and that contracts sometimes close before prime
contractors are required to show goodfaith in subcontracting with HUBs.
HUB participation in state procurement has declined over the last several
years and there is a concern that direct awards to HUBs by the state will
remain relatively low because these HUBs are unable to compete with large
businesses. The purpose of this bill is to strengthen the HUB
subcontracting program by creating greater accountability for noncompliance
with negotiated HUB goals by prime contractors.   

H.B. 1343 requires a prime contractor to submit subcontracting plans for a
procurement over $100,000. Under this bill, a prime contractor who does not
meet or exceed its negotiated HUB subcontracting goals, due to the lack of
a good faith effort, is subject to liquidated damages.    

RULEMAKING AUTHORITY

It is the opinion of the Office of House Bill Analysis that this bill does
not expressly delegate any additional rulemaking authority to a state
officer, department, agency, or institution. 

SECTION BY SECTION ANALYSIS

SECTION 1.  Amends Chapter 2161, Government Code, by adding Subchapter F,
as follows: 

SUBCHAPTER F.  SUBCONTRACTING

Sec. 2161.251.  APPLICABILITY.  (a) Provides that this subchapter applies
to all contracts entered into by a state agency with an expected value of
$100,000 or more, for the acquisition of a good or service and for the
construction of a public building, road, or other public work.  

(b) Provides that this subchapter applies to a contract without regard to
whether the contract is otherwise subject to this subtitle or the source of
funds for the contract. Provides that this subchapter does not apply if
federal law prohibits the application of this subchapter in relation to the
expenditure of federal funds used to pay for the contract. 

Sec. 2161.252. AGENCY DETERMINATION REGARDING SUBCONTRACTING OPPORTUNITIES;
BUSINESS SUBCONTRACTING PLAN.  (a) Requires a state agency considering
entering into a contract with an expected value of $100,000 or more to
determine before the agency solicits bids, proposals, offers, or other
applicable expressions of interest from prospective contractors (bids), if
it is probable that there will be subcontracting opportunities under the
contract. Requires the state agency, if it determines that there is that
probability, to require each bid to include a historically underutilized
business (HUB) subcontracting plan in its request for bids. 

(b)  Requires the state agency, if it determines there is a probability for
subcontracting opportunities under the contract, to determine the extent to
which HUB will be available  to enter into the subcontracts based on
specified information.  Requires the agency to state the minimum HUB
subcontracting goals for the contract expressed as a percentage of the
expected dollar value of the contract based on the expected value of the
subcontracting opportunities and its determination regarding the
availability of HUB to perform the subcontracted work. Requires the agency
to include the minimum percentage goal in its request for bids.  

(c)  Provides that, in the event that a state agency requires a HUB
subcontracting plan under Subsection (a), a bid must contain a plan which
that meets the requirements of this section in order for the bid to be
considered responsive. 

(d)  Provides that the HUB subcontracting plan is considered to be part of
the bid. Provides that the plan must include: 

(1)  the HUB subcontracting goal that the prospective contractor expects to
meet, expressed as a percentage of the expected dollar amount of the
contract; 

(2)  the name of each HUB with which the prospective contractor expects to
subcontract; 

(3)  the part of the work that each of those expected subcontractors would
perform; 

(4)  the expected dollar value of each subcontract; and

(5) information about the methods used in the past and present by the
prospective contractor to identify, contact, and evaluate available HUB
with which to subcontract.  

(e)  Provides that a prospective contractor's plan must account for the
possible event that the HUB subcontracting goal stated in the plan is less
than the state agency's stated minimum goal for the contract. Provides that
the plan must demonstrate the reason, in the prospective contractor's
opinion, for an insufficient number of HUB available in the locality to
allow the state agency's stated minimum goal to be met.  

Sec. 2161.253.  AGENCY EVALUATION OF BUSINESS SUBCONTRACTING PLAN. (a)
Prohibits a state agency which has required each bid for the contract to
include a HUB subcontracting plan from awarding the contract to a
contractor who did not include a plan in compliance with Section 2161.252.
Requires the state agency to evaluate and consider the merits of each
prospective contractor's HUB subcontracting plan when determining which bid
offers the best value to the state or is the lowest and best responsible
bid or proposal,.  

Sec. 2161.254.  REQUIRED CONTRACT CLAUSES.  (a) Requires a contract awarded
by a state agency that has required each bid, proposal, offer, or other
applicable expression of interest for the contract to include a HUB
subcontracting plan to include the contract clauses specified in this
section.  

(b)  Provides that the HUB subcontracting plan submitted by the prospective
contractor receiving the contract is considered to be part of the contract.
Provides that the HUB subcontracting goal is considered to be part of the
contract, except the negotiated goal is considered part of the contract if
negotiations were allowed under other law and the prospective contractor
and the state agency agreed on a different percentage subcontracting goal
during negotiations before the contract was awarded. 

(c)  Provides that the contract must require quarterly reports on the
progress the contractor is making in meeting the overall goals of the HUB
subcontracting plan.  Provides that the quarterly reports must generally
describe the progress being made in meeting the goals in the manner
prescribed by the state agency and report specified information. 

(d)  Provides that the contract must include a clause outlining and
describing the requirements of the state's HUB subcontracting program.  
 
(e)  Provides that the contract must include a liquidated damages clause
requiring the contractor to pay liquidated damages to the state after the
contract is completed if certain circumstances exist. 

(f)  Provides the formula for computing the amount of the liquidated
damages. 

Sec. 2161.255.  DETERMINING WHETHER TO ASSESS LIQUIDATED DAMAGES. (a)
Requires the purchasing personnel of the state agency, after completion of
the contract, to determine whether the value of subcontracts awarded under
the contract to HUB met or exceeded the HUB subcontracting goal that was
part of the contract.  Requires the agency, if it is determined that the
contractor failed to meet or exceed the goal, to notify the contractor of
that determination.  

(b)  Requires the state agency to give the contractor ample opportunity to
submit documentation and to explain how the failure to meet or exceed the
goal is not attributable to a lack of good faith effort to meet the goal.  

(c)   Requires the state agency's purchasing personnel, in determining the
extent to which the contractor made a good faith effort to meet the goal,
to consider specified factors indicating good faith on the part of the
contractor. 
   
(d)  Requires the state agency's officer or employee in charge of
procurement who determines after considering the documentation and
explanations submitted by the contractor that there was a lack of good
faith effort on the part of the contractor to meet the goal, to assess the
liquidated damages on behalf of the agency.  Requires the contractor to pay
the amount of the liquidated damages to the state agency, which is required
to send the money to the comptroller for deposit in the unobligated and
undedicated portion of the general revenue fund.  

SECTION 2.  Amends Section 2161.231, Government Code, as follows:

Sec. 2161.231.  PENALTY.  Provides that a person commits a third degree
felony if the person intentionally applies as a HUB for an award of a
subcontract under a purchasing contract or public works contract with a
state agency under this subtitle or other law and knows the person is not a
HUB.  

SECTION 3.Effective date: September 1, 1999. 
  Makes application of this Act prospective.

SECTION 4.Emergency clause.